lot_progress_6_26_04
Home ] Lot progress 4/12/04 ] Lot progress 5/22/04 ] Lot progress 5/29/04 ] Lot progress 6/7/04 ] lot_progress_6_18_04 ] [ lot_progress_6_26_04 ] lot_progress_7_6_04 ] lot_progress_7_18_04 ] lot_progress_7_26_04 ] lot_progress_8_7_04 ] lot_progress_8_16_04 ] lot_progress_10_8_04 ] lot_progress_2_20_05 ] PUPS_2_20_05 ] Cooper Holidays ] Building Outline ] Plan images ] Appliances ] Email ] GE appliances ] home depot ] lowes ] Google ]

 

Home
Lot progress 4/12/04
Lot progress 5/22/04
Lot progress 5/29/04
Lot progress 6/7/04
lot_progress_6_18_04
lot_progress_6_26_04
lot_progress_7_6_04
lot_progress_7_18_04
lot_progress_7_26_04
lot_progress_8_7_04
lot_progress_8_16_04
lot_progress_10_8_04
lot_progress_2_20_05
PUPS_2_20_05
Cooper Holidays
Building Outline
Plan images
Appliances
Email
GE appliances
home depot
lowes
Google

Status 6/26/04 : Ton of progress!!! ... Let see... 420gal tank has been ordered ... we got the tank from Aqua Art Aquariums... we will get it onsite in about 4 weeks... we also got the bottom floor wrapped in OSB... the master bath tub delivered ... the trussed delivered and set... Hmm what else.. oh yea ... all the fans and light fixtures bought ... so we are moving forward to make the deadline of Oct 31st... Now for the pictures...

Master room framing and bracing...

As we build on last weeks update .. we have completed the first floor framing except for the dead wood .. but we are mainly getting the house ready to place the Attic trusses...

Interior Wall framing and bracing...

the trick to the first floor framing is making sure it has all the hold downs... anchor bolts... straps... and plumbing in the walls .. next... is to get in all straight and plumb... this is done with all sorts of adjustable temp braces...

Window Header.....

In addition to the bracing all the proper headers and stud packs have to be installed... not to mention that all the doors and windows have to have the proper sized Rough openings placed in the correct spots ....

Bracing and Squaring the first floor....

The diagonal braces are only tacked in place by one nail that is not completely driven in.. so that it can be removed and the brace adjusted until the wall is plumb ... then tacked back to the brace stops...

First floor Framing and bracing..

As you can see from this picture there is a ton of braces ... in all different directions... once it is braced and adjusted ... they place the OSB sheathing...

Framers get the front porch beam installed...

The framers placed the LVL beams that are used to support the trusses on temp braces untill we get the columns ordered and onsite..

Kaylynn walks on water...

Look carfully at that picture above... do not ask me how .. but her feet are not touching the ground... you can see the shadows under her feet... but kaylynn is floating above the water in this picture... no tricks or touch ups ... talk about taking a picture at the perfect time...

Master Bath shower Framing...

Even the master shower and in master bath had braces ....

Rear of the house with porch beam and OSB sheathing...

Once all the braces are placed ... we wrapped the house with OSB 7/16" board with at nailing pattern of 3" o.c. edge nailing with 6" o.c. Field nailing... this is to provide the required wind shear strength...

exterior of the house wrapped with OSB...

Right side of the House sided with OSB...

Completly wrapped house with strack of trusses waiting to be placed...

Front of the house with OSB .. the front porch beam .. ready for the stack of trusses to be placed... 

The crane is about $105 dollars an hour to use ... well worth it..

The crane cost about 105 dollars and hour ... so the speed that the trusses can be placed is important to the framers... because we contracted with the framers to include the crane cost in there price... as well as their nails... this is very important for you to do ... it limits your costs... and motivates them to work fast and be careful with supplies...

Crane setting 43 Trusses...

The trusses where in place in less that 6 hours... was impressive to see them work...

the framers tacking the trusses in place as the crane brings them one after another..

The crane operator was very talented ... he did not sweep any of the framers off the walls... I listen to the talk about many stories about this happening at other job sites... 

Big expsenisive crane placing trusses..

The crane they used was massive for a residential home.... but the right tool for every job...

Crane drops in the next truss..

The house is starting to take shape....

Good view to see how large a room these attic trusses will provide up stairs..

It is a large room I will gain just by using attic trusses instead of common trusses... approximately 2100 sf of living space.. for about a 30% increase in truss cost... it was one hell of a deal...

End of the day the trusses are set.. and piggy backs are stacked to be placed...

Well as you can see the house is starting to look like a house.... and man we are getting excited... we are after all the parents to come up and visit us before we finish .. so they can see all that goes into the building of this house first hand.... then come back up after it is finished and stay with us in our new home...

Tricia runing home with her New Heater/massage unit from her new tub so no one takes it...

Tricia been a huge help on this project... doing odds and ends ... things that have to be done but seem to get over looked... god I love her... she is a wonder full wife.. Well that is all i have for now ... check back next Saturday and see how far we have progressed....

Later for now....

Mark